Timeline and Gantt

Schedule tasks, link them with dependencies and export the chart.

The timeline shows every dated task as a bar on a Gantt chart. Drag a bar to move a task, or drag its edge to change its duration.

Dependencies

A dependency says that one task depends on another. Tûm supports the four standard types:

TypeMeaning
Finish to start (FS)The next task starts once the previous one finishes. With no lag it can start on the same day. This is the most common type.
Start to start (SS)The next task starts when the previous one starts.
Finish to finish (FF)The next task finishes when the previous one finishes.
Start to finish (SF)The next task finishes when the previous one starts.

Lag and lead

Add a lag to wait a number of working days after the link, for example to let concrete dry. Use a negative value, called a lead, to let the next task overlap the previous one. Values range from -365 to 365 working days.

When a task moves, the tasks that depend on it move with it. Tûm refuses links that would create a loop.

Critical path and baselines

On the Pro plan, highlight the critical path: the chain of tasks where any delay pushes back the end of the project. Save a baseline to compare the current plan with the original one.

Date range

Use the date filter above the chart to focus on a period. The range is kept in the page address, so you can share or bookmark it.

Exporting the timeline

Choose Export in the timeline toolbar:

  • Image (PNG) for slides and messages.
  • PDF (print) opens your browser's print dialog. Choose landscape for wide schedules.
  • Vector (SVG) for documents that need to stay sharp at any size.

Each export carries the project name and the export date. Late tasks and tasks at risk keep their colour so the chart reads the same on paper.

On the Pro and Enterprise plans, exports also carry your workspace logo, ready to send to a client. Add or change the logo in Settings for the workspace. On the Free plan, exports end with a short "Made with Tûm" line instead.

To export all tasks with their fields, use Export to Excel on the project page.